Timeline for upcoming Robosub activities:
Wednesday, Jan 4th.
Andy will be finishing up some chassis connectors for the test on Thursday
Thursday, Jan 5th.
Bardia, Jay Jay, and Brian will be meeting at Mt. SAC at 9 am. Next, we will be picking up some plate steel and pipes from Ace Metal Supply in Chino.
expected end time: 10-10:30
After that, we will fabricate 2 new motor mounts and attach them to the sub.
expected end time 12:30
Testing in Bardia's pool to begin around 2 pm.
If new motor mounts cause the submarine to be unbalanced, extra weights will be attached in the front.
Ideally driving the submarine and shaping foam in order to compensate for drag.